
Mrs. Heins Advanced life skills class learned the importance of mise en place by prepping their toppings ahead of time and got hands on experience working with yeast to make pizza dough from scratch. One group even got creative and learned how to make a roux as an alternative to traditional red sauce for their breakfast pizza. So many great culinary skills being learned along the way!
Wednesday, November 11th
Fulda Public School Building Project Update
Over the past week and a half the pace of the work on the building project has picked up. Exterior wall framing on the North Addition is nearing completion and the first layer of sheathing is being put in place. Also in the North Addition all of the below ground plumbing has been placed awaiting inspection before the concrete floor is poured.
Work on the South Addition continued with the placement of the roof bar joists and decking. Exterior wall framing work is progressing, making way for the sheathing. In the Ag Shop, block work continues on the corridor that will provide access to the new Wood Shop.
Over the past several weeks progress has been made on the forming and placement of footings and foundation walls for the Gym/Storm Shelter. Tuesday, saw the arrival and placement of the first nine sections of the precast walls.
Throughout the site, work on the electrical, plumbing and mechanical systems continues. The upcoming weeks will see the roofers return, and concrete floors being poured in the North and South additions.
Monday, November 9th - Sunday, November 15th
Applications can be sent to:
Fulda Elementary
Attn: Brett Perish
303 N. Lafayette Ave
Fulda, MN 56131
Monday, November 9th
School is in session ALL DAY at both schools!
Elementary Conferences: By individually scheduled times.
High School Conferences: 3:30 PM–7:00 PM in the gym.
Tuesday, November 10th
School is in session ALL DAY at both schools!
Elementary Conferences: By individually scheduled times.
High School Conferences: 3:30 PM–7:00 PM in the gym.
The lost and found at the Elementary School is getting full. Do you recognize any of these items? Have your student stop by the office to claim their lost items.
Gavin Bell -12
Emily Gass - 11
Kaitlyn Wehking - 10
Daniel Thin - 9
Kole Appel - 8
Hayden Hardekopf - 7
Fulda Public School Building Project Update
This past week work on the framing of the North Addition exterior walls began. With the North Addition roof decking in place, the curbs, the structures that the rooftop HVAC units will be set on, were put in place.
This past week also saw the last of the building project footings being poured, these footings are for the Gym/Storm Shelter lobby area. Leveling of the fill and backfilling of the footings in the Gym/Storm Shelter was done in order to make way for the setting of the precast walls.
This past week plumbing work began in the North Addition and the Wood Shop while finishing up on the waste lines in the Science and Ag areas of the existing building. On the South Addition work continued on the placement of structural steel.
The Warriors boys' cross country team finished 4th overall, and the girls' team finished 11th. Great work!